Hillside Review Permits in Santa Rosa: What Homeowners Need to Know

If the area you want to build on in Santa Rosa slopes 10% or more, you will likely need a Hillside Development Permit from the Planning Department before the city will accept your building permit. It surprises a lot of homeowners, especially on smaller projects like a pool, an ADU or an addition. The good news: with the right documents and a team that knows the process, it is a predictable step. 

This guide explains what the Hillside Review is, what triggers it, what you need to apply, and how the process runs from application to approval. We also walk through a recent Affordable Drafting project that went through it this year. 

What is a Hillside Development Permit? 

A Hillside Development Permit is a planning approval, separate from your building permit, that Santa Rosa requires for new development on sloped ground. It comes from Chapter 20-32 of the Santa Rosa Zoning Code, the Hillside Development Standards. 

The city’s stated goals are to preserve Santa Rosa’s scenic character, protect open space and natural features, and make sure hillside projects respect the existing terrain, views and landforms. In practice, Planning wants to confirm that your project sits lightly on the slope: limited grading, stable soils, good drainage, and nothing that sticks out on a ridgeline. 

It is required in addition to every other permit. Until the Hillside Development Permit is approved, the Building Division will not accept your building permit application. 

What Triggers a Hillside Review? 

The trigger is a slope of 10% or more on the part of the site where you plan to build. A 10% slope rises 10 feet for every 100 feet of horizontal distance, which is gentler than most people expect. Many backyards that look “mostly flat” cross that line. 

A few things are worth knowing: 

It is about the work area, not the whole lot. The code applies to development “on that portion of a site with a slope of 10 percent or greater.” A steep back corner you are not touching does not count; a gentle-looking pad where the pool goes might. It applies to more than new houses. The review covers “all other proposed development or a new land use” on qualifying slopes. We have seen it apply to pools, ADUs, additions and retaining walls. 

Steeper ground carries tighter limits. Slopes over 25% that the city considers visually significant generally cannot be altered, and structures cannot interrupt the skyline from major public viewpoints. 

The city’s first answer is not always right. On a recent project, the city initially told us the threshold was 25%. We confirmed in the code that it is 10%, which changed the permit path before we had submitted anything. 

The slope must be calculated from an accurate topographic survey, and the city expects the slope analysis to be reviewed by a licensed civil engineer or surveyor. A rough estimate from a phone app or an old county map is not enough. 

What You Need to Apply 

A complete Hillside Development Permit application for a single-family project usually includes these items. Missing pieces are the most common cause of delay, so we assemble them before anything goes to the city. 

Item  What it shows  Who prepares it
Site plan  The project’s location and exact dimensions on the lot Your designer (ADS)
Topographic slope 

map

Two-foot contours, with areas under 10%, 10 to 25%, and over 25% marked Surveyor or designer, reviewed and stamped by a civil engineer
Preliminary 

geotechnical report

Soil and geologic conditions, with mitigation measures Geotechnical engineer
Project valuation  The estimated construction cost of the work Your contractor
Property owner’s 

consent form

The owner’s authorization for the application Property owner
Disclosure form  The city’s standard applicant disclosure Applicant

Subdivisions, multiple homes and nonresidential projects also need a visual analysis showing significant landforms and views from major public viewpoints such as Highways 101 and 12. A single home, ADU, pool or addition normally does not. The geotechnical report is usually the longest lead item. Order it early: the city will not take the application until it is in hand. 

The Process, Step by Step 

For one home, an ADU, a pool or an addition on an existing lot, the decision-maker is the city’s Zoning Administrator. Larger projects such as subdivisions go to the Planning Commission. Here is how a typical single-lot review runs. 

  • Confirm the slope. We survey the site, calculate the slope of the work area and confirm whether the 10% trigger applies. 
  • Meet with Planning (optional but helpful). A short meeting with city staff confirms what they expect to see and avoids surprises. 
  • Assemble and submit. The application goes to the Planning Department with the site plan, slope map, geotechnical report and forms. 
  • Completeness check and fees. Staff confirm the submittal is complete, collect the hillside application fee and assign a planner. 
  • Planner review. The planner reviews the project and sends comments. We revise the plans and resubmit, often within a day or two. 
  • Conditions of approval. The planner drafts the conditions the project must meet, and the applicant confirms they are accepted. 
  • Public notice. The city mails a notice to nearby property owners. It is routine, but it often surprises homeowners when the postcard arrives. 
  • Zoning Administrator decision. The project is presented at a scheduled Zoning Administrator meeting. The applicant can attend in person or by video, and neighbors may comment. 
  • Building permit. Once approved, the building permit application can finally be submitted and goes through normal plan check. 

Design Rules and Typical Conditions of Approval 

The hillside standards shape the design itself, so it pays to design with them from the start rather than fix a plan later. The main rules for a single-lot project: 

  • Siting. Place structures in the least visually prominent and most geologically stable part of the lot, at the lowest feasible elevation, aligned with the natural contours.
  • Stepped forms. Building pads should avoid large flat graded areas; the building should step with the terrain. 
  • Steep slopes. Slopes over 25% that the city identifies as significant generally stay untouched. 
  • Driveways. No steeper than 5% within 10 feet of a garage or carport entry, and an average finished grade of no more than 15%. 
  • Setbacks. Hillside setbacks are 20 feet in front and 15 feet at the sides and rear, measured from the top or toe of slope where a neighbor sits three or more feet higher or lower. ADUs are excepted from these hillside setbacks. 

The approval itself comes with conditions. These are the ones the city attached to our most recent hillside approval, a backyard pool: 

Condition  What it means for you
Grading limited to driveways, garage pads and areas under structures, including pools No extra terracing or leveling of the yard
Grading blends into natural contours; disturbed areas replanted with native plants Budget for slope grading and native landscaping
No grading on slopes over 10% from October 1 through April 30 Excavation must happen in the dry season, which can push a start date by months
Retaining walls (including pool walls) holding more than 6 feet of soil designed for seismic loads (CBC 1807.2.2) Engineering for taller walls
Stormwater LID determination worksheet with the building permit One more form at building permit stage
Geotechnical investigation and soils report with the building permit The final soils report must address grading, drainage, paving and foundations

The city also asked us to confirm that no trees would be removed, and a neighbor raised the same question. Keeping existing trees makes approval much smoother. 

A Real Example: A Backyard Pool on a Santa Rosa Hillside 

This year we took a homeowner’s new backyard pool through the Hillside Review. The Zoning Administrator approved it on October 8, 2026, about 14 weeks after we submitted, and we filed the building permit three days later.

 The yard looked close to flat, but our survey put the average slope of the pool area right at the 10% line. The city first told us the threshold was 25%. We checked the code, confirmed it was 10%, and changed course before anything was submitted. 

When (2026)  What happened
Early February  Pool design drawn; slope of the work area calculated at about 10%; Hillside Review confirmed as required
February  Civil engineer engaged to review and stamp the site plan and slope analysis
April  In-person meeting with city staff to confirm submittal requirements
July 1  Geotechnical report received
July 2  Hillside Development Permit application submitted
August 20  Planner’s review comments received; plans revised and resubmitted the next day
August 31  Second review complete; project scheduled for a Zoning Administrator meeting
Late September  Conditions of approval accepted; city mailed public notice to neighbors
October 8  Approved at the Zoning Administrator meeting (we attended by video)
October 11  Building permit application submitted

The longest single wait was the soils report, which took several months to complete. Once Planning had it, the review itself moved steadily. 

How Long It Takes, What It Costs, and How to Avoid Delays 

Plan on roughly three months in Planning once a complete application is in, then normal building plan check after that. The time before submittal depends mostly on how quickly the survey and geotechnical report come together. 

Costs come from three places: the city’s hillside application fee (set by Santa Rosa’s current planning fee schedule), the geotechnical engineer, and the civil engineer’s review and stamp of the slope analysis. Your drafting and permit coordination fees cover the rest. 

Tips that save the most time: 

  1. Check the slope before you design. Knowing early whether the 10% trigger applies shapes the budget and the schedule.
  2. Order the soils report first. It is usually the longest lead item, and nothing can be submitted without it. 
  3. Design to the standards. Step the project with the terrain, keep grading to the footprint and keep existing trees. 
  4. Answer comments fast. We turn planner comments around in a day or two so the file never sits. 
  5. Watch the calendar. Grading on slopes over 10% is not allowed from October 1 to April 30. An approval in the fall can mean waiting until spring to dig. 
  6. Expect the neighbor notice. It is routine. Telling neighbors about the project ahead of time heads off questions at the hearing. 

How Affordable Drafting helps 

We handle the Hillside Review from first survey to approval, so you are not left sorting out slope maps and planning comments on your own. 

Site survey and slope analysis. We scan and survey the site, build an accurate topographic model and calculate the slope of your work area. 

Design that fits the slope. Plans drawn to the hillside standards from the start, so there is less to fix in review. 

Coordination with consultants. We line up the civil engineer and geotechnical engineer and keep their work moving. 

Submittal and planner comments. We prepare and submit the application, answer comments quickly and attend the Zoning Administrator meeting.

 Straight on to the building permit. As soon as Planning approves, we submit for the building permit. Building on a slope in Santa Rosa? Contact Affordable Drafting to find out whether your project needs a Hillside Review and what it will take. 

 

Sources Santa Rosa City Code, Chapter 20-32: Hillside Development Standards. Chapter 20-32 summary on ecode360

This article is general information, not legal advice. Requirements change; confirm current rules and fees with the City of Santa Rosa Planning Division.